Preserving Turbomachinery During Construction Delays

Machines can wait months, sometimes years, between delivery and start-up. Preservation decides the condition they are in when the wait ends.

Rankine&Brayton Technical Solutions ยท

Turbomachinery preservation is the set of measures that protect a machine from corrosion, contamination and mechanical damage between delivery and start-up. During construction delays, preservation needs a written plan, regular inspections, complete records and a clear owner.

Large machines often arrive on site long before they are needed, and construction delays can extend that time further. Bearings, seals, shafts and internal surfaces can corrode or be damaged while the machine waits. These problems are often found only at commissioning, when they are most expensive to fix.

Start with the OEM's requirements

The OEM's preservation instructions define what the machine needs, and are usually linked to its warranty. They typically cover storage conditions, preservatives, desiccants, rotor turning intervals, inspection frequency and the period for which the factory preservation remains effective.

Write a site preservation plan

  • Which machines and auxiliaries are covered, and where they are stored.
  • Storage conditions: indoor or outdoor, covers, ventilation and, where required, heating or dehumidification.
  • Preservation tasks and their frequency, such as rotor turning, desiccant checks, nitrogen purge pressure or oil circulation.
  • What happens when preservation must be extended beyond the OEM's original period.
  • Who performs each task, who checks it and who keeps the records.

Inspect and record

Preservation that is not recorded cannot be demonstrated. Each inspection should record the date, the condition found, the tasks performed and any defects, with photographs where useful. Missing records can create disputes over warranty and responsibility later.

Installed but idle

Machines that have been set and aligned but not commissioned need special attention. They are often exposed to construction activity, dust, water and welding. Openings should stay sealed, and preservation tasks continue until the machine enters commissioning.

Handover of responsibility

Responsibility for preservation often passes between the OEM, the logistics provider, the EPC contractor and the owner. Each handover should be formal, with the condition of the machine and the preservation records accepted by the receiving party.

Before commissioning

Before the machine is started, the preservation must be removed or neutralized as the OEM requires, and the machine inspected. A review of the preservation records at this point helps confirm the machine is ready.

Quick answers

What is turbomachinery preservation?

The measures that protect a machine from corrosion, contamination and mechanical damage between delivery and start-up.

Who is responsible for preservation on site?

It depends on the contract. Responsibility often passes between the OEM, the logistics provider, the EPC contractor and the owner, so each handover should be formal and documented.

This article is general information. Follow the OEM's preservation instructions for the equipment concerned.

Rankine&Brayton Technical Solutions

Independent turbomachinery consulting company. Our senior consultants support gas turbine, steam turbine and compressor projects from front-end definition through RFSU and turnover.

Contact

Need a second view on your project?

A 30-minute call to speak about the current status of your project and how we can support you. No obligation, and everything you share stays confidential.

Request a consultation